Differential Settlement. - Its Causes and How to Prevent it
Total settlement of a foundation consists of:
1. Immediate settlement
2. Consolidation settlement
3. Secondary consolidation settlement
The immediate settlement is also known as elastic settlement. It can be found by elastic theory as,
Se = qn B
where qn = Net foundation pressure B = Width of foundation
m = Poisson’s ratio Es = Modulus of elasticity
qn = Influence factor which depends upon ratio of the foundation and the thickness of
compressible layer
Consolidation settlement may be found by
where H = Thickness of compressible layer
Cc = Compression index
eo = Initial void ratio
Po = Initial overburden pressure
Dp = Increase in the pressure due to load
Secondary consolidation settlement is small and takes place over a long period.
Plate Load Test
By loading a rigid square plate in a pit with reaction frame this test is conducted to measure the
settlement. The following points may be noted:
1. The minimum size of plate 300 mm. Commonly used plate sizes are 300 mm, 450 mm and 600 mm.
2. It is preferable to use 600 mm square plate for fissured clays and relatively loose sands and silts.
3. Width of the test pit should be at least 5 times the plate side.
4. The plate should be at the level of actual foundation proposed.
5. IS code recommends a preliminary seating load of 70 gm/cm2 before the main test.
6. Apply the load in increments and measure the settlement with dial gauge. The maximum load
corresponds to times the estimated ultimate load.
7. In cohesionless soil each incremented load is maintained for at least one hour before the settlement.
On clayey soil the load is maintained until about 75% of probable settlement has reached or for 24
hours.
8. Load settlement curve is plotted and ultimate bearing capacity is found as the load corresponding
to the settlement after which settlement rate is fast. If load-settlement curve does not indicate a
marked breaking point, a settlement equal to of the width of the test plate is considered the
failure point.
* According to IS code the permissible values of settlements in clays and sands are 40 mm and 25
mm respectively.